Once the supplier has accepted and sent the deposit invoice - right click to create the deposit invoice
Once the product has arrived it can be removed from this dashboard
...
Internal Manufactured items
...
Quantity will be the order lineThe production process linked to the top level item will create Production steps
Builds are one per item - so a qty = 2 will create 2 build jobs
Build Steps are created
Where a component has a TAG that tag will be respected to add or remove production steps
Example
Production Process step “sew cushion full cover” is only required when feathers are chosen
Feather choice has a tag of “F”
Production step has a tag of “F” and is set to “Include only with TAG”
So a 2 Seater sofa with a feather fill seat will have an additional step of sewing cushion covers
Production Planning
Jobs priority is based on
...